Sr. No. |
Number of schemes | Estimate/
Approved Cost |
Expenditure (31-12-2018) | Physical Progress (%) | Remarks |
I | Punjab | ||||
1 | Extension of existing J-Head Spur by 2400 feet at RD 188+000 of Link No. 1 | 133.597
29/03/2018 |
N.R | N.R | * Work awarded.
* Likely to be started shortly |
2 | Construction of 09 Nos. stone studs to protect vilaages and abadies (Manjhota, Sawang, Sasti and Sangi) from flood flows of Sanghar Hill Torrent | 55.431
07/03/2018 |
N.R | N.R | * Work awarded.
* Likely to be started shortly |
3 | Checking erosion from RD 458 to 465 Extension Minchin Flood Bund in Dallas Canal Division Rahimyar Khan | 136.906
29/03/2018 |
N.R | N.R | Tendering stage |
4 | Checking erosive action of River Chenab near Shakar Kot and Randhir Khokran villages along right bank of River Chenab | 198.253
Under process for approval |
– | – | PC-I under preparation with PID, Punjab |
5 | Construction of diversion structures on River Jhelum near Gaga, village, Tehsil Bhera | 15.070
Under process for approval |
– | – | Scheme dropped by PID, Punjab |
Sub Total | 524.187 | ||||
II | Sindh | ||||
6 | Providing Stone Pitching along Baiji Bund mile 2/4 to 3/4 and 7/4 to 8/4 in Ghotki District. | 58.423
7/01/2016 |
39.678 | 100% | Completed |
7 | Proposal for closing breach mile 1/1 to 2/6 Qadirpur Shank Bund, Shank Projection mile 0/o to 0/3, raising & strengthening mile 0/0 to 1/2 Qadirpur bund, Qadirpur Shank bund mile 0/0 to 1/7 and providing stone pitching mile 1/7 to 2/6 Qadirpur Shank bund and Shank Projection mile 0/0 to 0/3 R/s (Breach Portion) | 259.112
11/02/2016 |
206.028 | 100% | Completed |
8 | Providing stone apron along Qadirpur loop bund mile 10/4 to 11/4 | 160.000
4/08/2016 |
48.300 | 90% | Lagging behind schedule |
9 | Providing Stone Apron, Stone Pitching 4 Nos Stone Stud and Earth Work along Moria Loop Bund mile 0/0 to 1/0 in Northern Dadu Division, Larkana. | 201.110
4/08/2016 |
108.843 | 97% | Lagging behind schedule |
10 | Providing Stone Pitching and Stone Apron along Qadirpur Loop Bund Mile 7/2 to 8/4. | 202.412 | Nil | Nil | Scheme was cleared in S.C meeting on 19.11.2018.
Modified PC-I awaited |
Sub Total (Sindh) | 881.057 | 404.370 |