MONITORING PROGRAMME FOR SCHEMES IMPLEMENTED BEING IMPLEMENTED UNDER NORMAL /EMERGENT FLOOD PROGRAMME |
|||||
Sr. No. | Name of Scheme | Approved Cost | Physical Progress | Visit Carried out by FFC’s Team | Schedule of FFC’s Team visit |
Approval Date | Expenditure | ||||
I | PUNJAB | ||||
Carry forwarded from previous years | |||||
1. | Channelization of Deg Nullah (Estimated Cost Rs. 2,350.533 million) | 2350.553
04/08/2016 |
– | – | 1st Week of February 2019 |
2. | Checking erosion action of Chenab River of left bank near Gangwal, Papin village U/s Marala Barrage, District Sialkot | 171.613
31/03/2015 |
100%
138.594 |
13-02-2016
25-03-2017 |
|
3. | Correcting approach of River Chenab to Control erosive action along its R/B opposite RD 0+000 Muzaffargrah F/B to RD 131+500 Khangarh F/B in District Muzaffargarh | 290.812
18/03/2010 29/12/2012 11/04/2017 |
– | 21-11-2016 | 2nd Week of February 2019 |
4. | Protecting Irrigation System Near Head Regulator Bakaini, Area of Bait Daryai and Gabbar Arain from Hectic Erosive Action of Indus River (Revised),
District. Muzaffargarh |
532.440
18-06-2012 29-10-2015 |
92%
426.554 |
04-05-2014 | |
5. | Construction of J-Head Spur at RD 20+000 and Guide Head Spur at RD 25+000 Magasson Branch,
District Muzaffargarh |
513.339
11/04/2014 |
59%
239.480 |
16-03-2015
31-12-2015 |
3rd Week of February 2019 |
6. | Restoration of J-Head Spur at RD-165+000 of Link No. 1, District. DG Khan | 246.980
20/05/2016 |
85%
39.324 |
20-06-2018 | |
7. | Restoration of J-Head Spur at RD-167+000 of Link No. 1, District. DG Khan | 144.950
20/05/2016 |
100%
56.043 |
20-06-2018 | |
2017-18 | |||||
1. | Checking erosion from RD 458 to 465 Extension Minchin Flood Bund in Dallah Canal
Division Rahimyar Khan |
136.906
29/03/2018 |
0%
Nil |
Not yet started | Delayed |
2. | Extension of existing J-Head Spur at RD 188+000 of Link No. 1, Tehsil Kot Chutta,
District D.G.Khan |
133.597 | 25%
Nil |
Not yet conducted | 3rd Week of February 2019 |
29/03/2018 | |||||
3. | Construction of 09 No. stone stud to protect villages and abadies (Manjhota, Swang, Sasti and Sangi) from flood flows of Sanghir Hill Torrent. | 55.431
07/03/2018 |
20%
Nil |
Not yet conducted | |
2018-19 | |||||
1. | Checking erosive action of River Chenab near Shakar Kot and Randhir Khokran villages along right bank of River Chenab | 198.253 | PC-I under process for approval | ||
II | SINDH | ||||
Carry forwarded from previous years | |||||
1. | R&S along U/S Right Marginal bund from mile 0/0 to 5/4 & U/S Right spur Bund mile 0/0 to 3/0 (District Kashmore) | 57.029
13/3/2015 |
100%
57.522 |
12-12-2015 | 1st Week of February 2019 |
2. | Providing stone apron and pitching along sukkur beghari bund mile from 0/0 to 2/0 vulnerable point sukkur city
(District Sukkur) |
127.084
21/12/2015 |
100%
135.202 |
18-07-2016
27-11-2016 19-01-2017 15-03-2017 29-11-2018 |
1st Week of February 2019 |
3. | Providing Stone Apron along Qadirpur Loop Bund mile 4/6 to 5/0
(District Ghotki). |
32.274
7/1/2016 |
100%
20.179 |
19-07-2016
26-11-2016 20-01-2017 16-03-2017 28-11-2018 |
1st Week of February 2019 |
4. | Providing Stone Pitching along Baiji Bund from mile 2/4 to 3/4 and 7/4 to 8/4
(District Ghotki). |
58.423
7/1/2016 |
100%
39.678 |
19-07-2016
26-11-2016 28-11-2018 |
– |
5. | Closing breach mile 1/1 to 2/6 Qadirpur Shank Bund, Shank project mile 0/0 to 0/3, Raising & Strengthening mile 0/0 to 1/2 Qadirpur Bund, Qadirpur Shank Bund mile 1/7 2/6 Qadirpur Shank Bund and Shank Projection mile 0/0 to 0/3 R/S (Breach Portion) (District Ghotki). | 259.112
11/2/2016 |
100%
206.028 |
19-07-2016
26-11-2016 20-01-2017 16-03-2017 28-11-2018 |
– |
6. | Providing Stone Apron along Qadirpur Bund mile 10/4 to 11/4 District Ghotki | 160.00
4/8/2016 |
90%
49.821 |
28-11-2018 | 1st Week of February 2019 |
7. | Providing Stone Apron, Stone Pitching and earthwork along Moria Loop Bund mile 0/0 to 1/0 in Northern Dadu Division
Larkana. |
201.11
4/8/2016 |
97%
108.843 |
30-04-2017
27-11-2018 |
– |
2018-19 | |||||
1. | Providing stone pitching and stone apron along Qadirpur Loop Bund mile 7/2 to 8/4 | 219.802 | PC-I under process for approval | ||
III | KHYBER PAKHTONKHWA | ||||
Previous Years | |||||
1. | Construction of Flood Protection Structure at critical locations in different Nullahs in District Peshawar and Nowshera. | 30.00
13/03/2015 |
100%
30.530 |
16-10-2015 | 4th Week of February 2019 |
2. | Construction of Flood Protection Structure at critical locations in different Nullahs in District Swat. | 19.868
4/5/2015 |
100%
16.242 |
02-08-2016 | 4th Week of February 2019 |
3. | Construction of Flood Protection Structure at critical locations in different Nullahs in District Abbottabad and Mansehra. | 10.00
4/5/2015 |
68%
8.65 |
04-01-2016
20-03-2017 |
1st Week of March 2019 |
4. | Construction of Flood Protection Structure at critical locations in different Nullahs in
District Kohat & Karak. |
9.63
13/3/2015 |
100%
6.90 |
06-02-2016 | 1st Week of March 2019 |
5. | Construction of Flood Protection Structure at critical locations in different Nullahs in
District Bannu & Lakki Marwat. |
12.50
4/5/2015 |
100%
12.5 |
Not yet conducted | 1st Week of March 2019 |
6. | Construction of Flood Protection Structure at village Kala on Badri Nullah
District Swabi. |
6.106
13/3/2015 |
60%
6.106 |
18-11-2015
23-04-2016 31-01-2017 |
3rd Week of February 2019 |
7. | Construction of flood protection structures for protection of Dheri village on Dheri Jolagram Nullah District Malakand | 10.84
13/3/2015 |
100%
8.089 |
05-01-2016
01-08-2016 |
1st Week of March 2019 |
8. | Construction of Flood Protection Bund for protection of village Yark in Takwara nullah
District D.I. Khan |
20.82
03/02/2017 |
100%
21.80 |
15-04-2017
18-11-2017 |
1st Week of March 2019 |
9. | Providing flood protection works in Kurram River District Bannu | 10.00
12/5/2016 |
100%
8.50 |
13-10-2016 | 1st Week of March 2019 |
10. | Flood Protection Works for Protection of Village Abadies Agriculture land from flood flows in river/ Nullahas District Lakki Marwat | 16.00
12/5/2016 |
100%
10.843 |
04-02-2017
11-03-2017 |
2nd Week of February 2019 |
11. | Construction of flood protection works for protection of village abadies and agriculture land on Pir Khel Totakan Khawa | 6.00
09/06/2016 |
100%
4.05 |
Not yet conducted | 2nd Week of February 2019 |
12. | Construction of flood protection works in Ayyun, Jaghur Kuru and Bamburait area,
District Chitral |
9.952
03/02/2017 |
100%
7.557 |
Not yet conducted | 2nd Week of February 2019 |
13. | Construction of flood protection work for: (i) Construction of flood protection work in Siran River near Malik Pur vilalge, District Manshera. (ii) Construction of flood protection work in Haro River Check Kamal Pur U/C Hattar District Haripur. (iii) Construction of flood protection work alongwith Indus River (left side) village Jammu Ghazi Area, District Haripur | 7.00
12/05/2016 |
100%
7.00 |
20-03-2017 &
21-03-2017 |
2nd Week of March 2019 |
14. | Construction of flood protection work at Sawaldher Bakrai Khpa, District Mardan | 7.00
03/02/2017 |
39%
1.612 |
15-11-2017 | 2nd Week of February 2019 |
15. | Construction of flood protection wall along Panjpir Madarassa & village on left Bank of Badri Nullah, District Swabi | 7.00
09/06/2016 |
100%
7.00 |
16-11-2017 | 2nd Week of February 2019 |
16. | Providing flood protection works in different Nullahs in District Dir (Lower) | 10.00
12/05/2016 |
100%
9.439 |
Not yet conducted | 2nd Week of February 2019 |
2016-17 | |||||
1. | Construction of Flood Protection Work at critical locations in Chitral Irrigation Division,
District Chitral |
17.30
03/02/2017 |
93%
14.683 |
Not yet conducted | 1st Week of April 2019 |
2. | Construction of Flood Protection work along Bahar Nullah for the protection of Mardan Dobian Road and village abadies of District Mardan | 10.00
03/02/2017 |
100%
8.156 |
15-11-2017 | 2nd Week of February 2019 |
2017-18 | |||||
1. | Construction of flood protection work on right side of Ismail drain in Ismaila Village
District Swabi |
8.663
7/03/2018 |
65%
4.655 |
Not yet conducted | 2nd Week of February 2019 |
2. | Construction of flood protection bund for protection of village abadies of Yarik U/S & D/S of NHA Road in Takwara Nullah District D.I. Khan | 4.80
7/03/2018 |
60%
1.20 |
08-12-2018 | 3rd /4th Week of February 2019 |
3. | Construction of flood protection bund for the protection of village Shero Wanda Panyala Area
District D.I. Khan |
4.50
7/03/2018 |
20%
Nil |
08-12-2018 | 3rd / 4th Week of March 2019 |
4. | Flood protection work for protection of village abadies & agriculture lands of Kotka Malakan village Mama Khel Wali Noor Jani Khel form Ghundaki Algada & Zafer Ali Khan Junai baka Khel from Tochi River in
District Bannu |
9.760
7/03/2018 |
100%
|
Not yet conducted | 3rd / 4th Week of March 2019 |
5. | Construction of flood protection work for protection of Land & Abadies from flood flows in Varmola & Nugram Nullah in
District Lakki Marwat |
5.00
7/03/2018 |
100% | 14-09-2018 | 3rd / 4th Week of March 2019 |
6. | Construction of protection bund in Wanda, Zalo and Malagan, Tehsil &
District Tank. |
5.90
7/03/2018 |
70%
3.00 |
08-12-2018 | 3rd / 4th Week of March 2019 |
7. | Construction of Flood Embankment Protection works for protection of village abadies near village Khanay Bakka Khel and adjoining agriculture lands from flood flows in Tochi River,
District Bannu |
10.00
7/03/2018 |
100% | Not yet conducted | 3rd / 4th Week of March 2019 |
2018-19 | |||||
1. | Construction of flood protection work along Chital River at Green Lasht & Roshun
District Chitral |
13.498 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
2. | Construction of flood protection work for the protection of agriculture land along right bank & protection of Lodhi Khel Channel along left bank of Khanki Toi & Shahu Bazar,
District Hangu. |
6.830 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
3. | Construction of flood protection works along Barando River in
District Buner |
10.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
4. | Construction of flood protection works downstream of Fizzaghat along left bank of Swat River in District Swat | 20.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
5. | Construction of flood protection work for protection of agricultural lands U/S & D/S of causeway along Ismaila Drain (Naranji Nullah) in village Ismaila, District Swabi | 15.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
6. | Construction/ Improvement of flood protection works along Bullar Nullah for protection of Daulat Minor at RD-40000-49500 and agricultural land, village abadies at village Gidar (Mahmood Abad), Gumbat and Kandar Area | 15.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
7. | Construction of flood protection structures at vulnerable locations of rivers and its tributaries in Bannu & Lakki Marwat Districts | 25.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
8. | Construction of flood protection structures at vulnerable locations of rivers and its tributaries in Bannu & Lakki Marwat Districts
|
25.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
IV | BALOCHISTAN | ||||
2015-16 | |||||
1. | Construction of flood protection wall Killi Noroz Khan and others, District Kohlu | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st /2nd Week of March 2019 |
2. | PC-I for construction of flood protection gabion wall along killi Mohibullah Khan Matyan Malik Gul Jan & others Droog area, District Musa Khel | 2.00
12/05/2016 |
80%
1.120 |
Not yet conducted | 1st /2nd Week of March 2019 |
3. | Construction of flood protection wall for Tabab Shah Killi Shaikhan, District Harnai | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 1st /2nd Week of March 2019 |
4. | Construction of flood protection wall of Killi Dargai Zardaloo Area, District Harnai | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 1st /2nd Week of March 2019 |
5. | Construction of protection wall for Khost Bazar, District Harnai | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st /2nd Week of March 2019 |
6. | Construction of flood protection Bund Maree Sui Area, District Dera Bughti | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st /2nd Week of March 2019 |
7. | Construction of flood protection wall for agriculture land of Haji Abdul Raheem Chanali area, District Loralai | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 1st /2nd Week of March 2019 |
8. | Flood protection wall killi kach Sodozai Abdul Looni Tehsil Duki,
District Loralai |
1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 1st /2nd Week of March 2019 |
9. | Flood protection (Stone Masonry wall) for the lands of Karez Akhwanzada Killi Mughtian Bostan area, District Pishin | 1.50
12/05/2016 |
100%
0.00 |
8-05-2017 | 1st /2nd Week of March 2019 |
10. | Flood protection gabion wall for the land of Ameer Jan orchards lands Surkach Killi Dilsora Khandozai, District Pishin | 1.50
12/05/2016 |
100%
1.50 |
8-05-2017 | 1st /2nd Week of March 2019 |
11. | Construction of flood protection wall of Malik Rud Mulla Zai area,
District Pishin |
1.50
12/05/2016 |
100%
1.50 |
8-05-2017 | 1st /2nd Week of March 2019 |
12. | Construction of flood protection wall for Agriculture land of Dr. Bashir Kakar Kanozai Balozai area, District Pishin | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st /2nd Week of March 2019 |
13. | Flood protection work for Agriculture land of Rashid Khan Nasir Killi Nasiran Bostan area, District Pishin | 1.50
12/05/2016 |
100%
1.50 |
8-05-2017 | 1st /2nd Week of March 2019 |
14. | Construction of flood protection of Haji Muhammad Din Tareen Darag for protection of houses/agriculture land Kan Bunglow District Ziarat | 1.00
12/05/2016 |
100%
1.00 |
9-05-2017 | 1st /2nd Week of March 2019 |
15. | Construction of flood protection wall Jangeer Khan Zina area, District Ziarat | 1.00
12/05/2016 |
100%
1.00 |
9-05-2017 | 1st /2nd Week of March 2019 |
16. | Construction of flood protection wall for agriculture land of Molvi Ghousdin and Haji Dewan Tandwani Chotair area,
District Ziarat |
1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st /2nd Week of March 2019 |
17. | Construction of flood protection wall/Bund for agriculture land of Yahya Khan and Sheri Yar Khan village Zindra District Ziarat | 2.00 | 85%
0.90 |
Not yet conducted | 1st /2nd Week of March 2019 |
18. | Flood protection wall for water supply scheme in Tabbai Nohisar, District Quetta | 1.00
12/05/2016 |
100%
1.00 |
11-05-2017 | 3rd / 4th Week of March 2019 |
19. | Flood protection wall in Aghbarg area for killi Ghabizai, District Quetta | 1.00
12/05/2016 |
100%
1.00 |
11-05-2017 | 3rd / 4th Week of March 2019 |
20. | Flood protection wall in Sara Ghurgai for Agriculture lands Shair Jan Bazai and others, District Quetta | 1.00
12/05/2016 |
100%
1.00 |
11-05-2017 | 3rd / 4th Week of March 2019 |
21. | Flood protection wall in Baleli area for Agriculture lands Abdul Raziq Khan & others, District Quetta | 1.00
12/05/2016 |
100%
1.00 |
11-05-2017 | 3rd / 4th Week of March 2019 |
22. | Construction of flood protection wall in Allah Gul Shamsozai Pashton Bagh Kharot Abdab for agriculture, District Quetta | 1.25
12/05/2016 |
100%
1.25 |
11-05-2017 | 3rd / 4th Week of March 2019 |
23. | Construction of flood protection scheme of Taw Wal Killa Nawab Muhammad Khan and Umer Khitab and Khusro Jogezai, District Killa Saifullah | 1.00
12/05/2016 |
100%
1.00 |
10-05-2017 | 3rd / 4th Week of March 2019 |
24. | Construction of flood protection wall in Bundat Musazai Murad khan and others, District Killa Saifullah | 1.00
12/05/2016 |
100%
1.00 |
10-05-2017 | 3rd / 4th Week of March 2019 |
25. | Flood protection of Agriculture land/Houses of Mohammad Hanif and others Ragha Sultanzai Muslim Bagh area, District Killa Saifullah | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 3rd / 4th Week of March 2019 |
26. | Flood Protection of Agriculture land of Killa Mulla Baz Wali Rud Jogezai area, District Killa Saifullah | 1.25
12/05/2016 |
100%
1.25 |
Not yet conducted | 3rd / 4th Week of March 2019 |
27. | Construction of flood protection gabion wall along Killi Dabari (Ikhlas Khan) Chaman area, District Killa Abdullah | 1.50
12/05/2016 |
100%
0.72 |
Not yet conducted | 1st / 2nd Week of April 2019 |
28. | Construction of flood protection Bund for Washuk town, District Washuk & Kharan | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of April 2019 |
29. | Construction of flood protection Bund for Rehmatullah Baloch Bandband , District Washuk & Kharan | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of April 2019 |
30. | Construction of flood protection wall Usmanabad Balinna, Kattan area, District Khuzdar | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 1st / 2nd Week of April 2019 |
31. | Construction of flood protection Bund for Bulanzer Kehan Zehri area, District Khuzdar | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
32. | Construction of flood protection wall/bund Killi Khuda Bukhsh Khandozai Nal Khuzdar, District Khuzdar | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
33. | Construction of flood protection Bund Killi Soorgaz Muhammad Umer Khuzdar, District Khuzdar | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
34. | Flood protection wall for agriculture land/houses in Iskalkoo area, District Kalat | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
35. | Flood protection wall for agriculture land/houses in Johan area village Haji Muhammad Alam Bungulzai, District Kalat | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
36. | Flood protection wall Killi Sheikhan, District Mastung | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
37. | Flood Protection wall for Ispilingi area, District Mastung | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 1st / 2nd Week of April 2019 |
38. | Construction of flood protection bund Sheenh Lakhi Bent in Tehsil Dureji,
District Lasbela |
1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
39. | Construction of flood protection bund at Main Lasbela Canal Near Minor No. 2 in Sakran Tehsil Hub, District Lasbela | 1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
40. | Construction of flood protection bund for agriculture land/Houses of Goth Qazi Ghulam Muhammad Bela, District Lasbela | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 3rd / 4th Week of April 2019 |
41. | Construction of flood protection wall for Killi Haji Abdul Hakeem Pirkoh, Bela, District Lasbela | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 3rd / 4th Week of April 2019 |
42. | Construction of flood protection work Mir Zahoor Ahmed Buladi, Buleda, District Kech | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
43. | Construction of flood protection work Ginna Turbat, District Kech | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 3rd / 4th Week of April 2019 |
44. | Construction of flood protection bund Chitkan Mainwar Gharibabad, District Panjgoor | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
45. | Completion of flood protection bund of killi Haji Muhammad Azim Sabzap (Phase-II), District Panjgoor | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
46. | Construction of flood protection bund Basool Kaur Ormara, District Gawadar | 2.00
12/05/2016 |
100%
2.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
47. | Construction of Agha Haroon Flood Protection Bund for Killi Jan Agha, District Nushki | 1.50
12/05/2016 |
100%
1.50 |
Not yet conducted | 3rd / 4th Week of April 2019 |
48. | Construction of flood protection Bund for agriculture lands of Sofi Allah Rakha S/o Rasool Bukhsh Kalwar and other Mouza Ganmb Tehsil Bhag, District Kachhi | 1.50
12/05/2016 |
0%
0.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
49. | Construction of flood protection Bund around the houses of Killi Dargha Sufi Ahmed Faqir Bhag town area,
District Kachhi |
1.00
12/05/2016 |
100%
1.00 |
Not yet conducted | 3rd / 4th Week of April 2019 |
2016-17 | |||||
50. | Construction of flood protection spurs along left bank of Nari River for protection of agricultural lands and abadies of village Malik Muhammad Akhtar and others,
(District Sibi). |
10.00
03/02/2017 |
100%
9.198 |
Not yet conducted | 1st / 2nd Week of May 2019 |
51. | Construction of flood protection bund for houses and agricultural lands at Pashtoon Bagh, (District Quetta) | 2.00
03/02/2017 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of May 2019 |
52. | Construction of flood protection bund Sayani Dohra at Muhammad Seyapad Goth Pirkas Tehsil Hub, (District Lasbella) | 2.50
03/02/2017 |
100%
2.50 |
Not yet conducted | 1st / 2nd Week of May 2019 |
53. | Construction of flood protection wall for Gullo Goth Shah Noorani area Tehsil Wadh,
(District Khuzdar) |
15.00
03/02/2017 |
80%
8.302 |
Not yet conducted | 1st / 2nd Week of May 2019 |
54. | Construction of flood protection PCC wall for agricultural land and houses along Gaitanai Kaur Washbood,
(District Panjgoor) |
2.50
03/02/2017 |
100%
2.50 |
Not yet conducted | 1st / 2nd Week of May 2019 |
55. | Construction of flood protection wall for agricultural land of village Karmabad along left bank of Sehab River, (District Loralai) | 2.00
03/02/2017 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of May 2019 |
56. | Construction of flood protection of agricultur land of Fateh Muhammad and others of Apozai (District Zhob). | 2.00
03/02/2017 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of May 2019 |
57. | Construction of flood protection wall for Killi Sikandar abad Dairy Farm area, (District Kohlu) | 2.00
03/02/2017 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of May 2019 |
58. | Construction flood protection wall for houses Killi Biber Tak area,
(District Barkhan) |
2.00
03/02/2017 |
100%
2.00 |
Not yet conducted | 1st / 2nd Week of May 2019 |
2017-18 | |||||
59. | Construction of flood protection for Patar Colony at Hub,
District Lasbella |
39.60
7/03/2018 |
100%
39.206 |
Not yet conducted | 2nd Week of February 2019 |
2018-19 | |||||
1. | Flood protection bund for Sardari Sher Whad, District Khuzdar | 25.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
2. | Flood protection bund for Shah Norani
District Khuzdar |
25.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
3. | Flood protection bund for Jhal Magsi Town,
District Jhal Magsi |
30.00 | PC-I under process for approval
(Site visit in 3rd / 4th Week of June 2019) |
||
V | GILGIT-BALTISTAN | ||||
Carry forwarded from previous years | |||||
1. | Construction of flood protective and river training works for Darel / Tangir valley,
District Diamer. |
30.90
5/4/2007 |
90%
23.315 |
Not yet conducted | 3rd Week of February 2019 |
2. | Construction of protective bunt at Ghursey
(Ph-IV), District Ghanche |
24.113
17/05/2012 |
65%
8.492 |
30-08-2016 | 1st Week of April 2019 |
3. | Construction of protective works at Surmo
(Phase-III), District Ghanche. |
16.428
17/05/2012 |
87%
13.192 |
30-08-2016 | 1st Week of April 2019 |
4. | Construction of flood protection works at Pakora Hoto, (Revised)
District Skardu |
25.00
4/05/2016 |
99%
20.50 |
29-08-2016 | 1st Week of April 2019 |
VI | FATA | ||||
2016-17 | |||||
5. | Construction of flood protection bund for protection of land of Inayat-Ur-Rehman Kach on Tank Zam South Waziristan Agency (SWA). | 7.357
03/02/2017 |
100%
7.323 |
Not yet conducted | 3rd / 4th Week of February 2019 |
6. | Construction of flood protection bund for protection of land of Sher Jan Kach, Noor Gul Kach and Niazam Gul Kach on Gatt Algad in Sherani area,
FR D.I.KHAN |
7.359
03/02/2017 |
100%
7.329 |
Not yet conducted | 3rd / 4th Week of February 2019 |
7. | Construction of flood protection bund for protection of land of Anwar Kach on Local Algad in Sherani Area FR D.I.KHAN | 6.170
03/02/2017 |
100%
6.138 |
Not yet conducted | 3rd / 4th Week of February 2019 |
8. | Flood protection scheme for the land of Asghar & Mulvi Rashid Kach in KAZA Nar near Torwan area/land near Torwan Bridges in Tiarza Tehsil South Waziristan Agency (SWA). | 8.00
03/02/2017 |
100%
7.964 |
Not yet conducted | 3rd / 4th Week of February 2019 |
9. | Flood protection scheme Raza Kach on Kurram River Shewa Tehsil
North Waziristan Agency (SWA) |
7.00
03/02/2017 |
100%
4.40 |
30-05-2018 (Monitoring by FATA Directorate) | 3rd / 4th Week of February 2019 |
10. | Flood protection scheme in Kurram agency: | 6.00
03/02/2017 |
100%
1.748 |
27-09-2018
29-08-2018 (Monitoring by FATA Directorate) |
3rd / 4th Week of February 2019 |
2017-18 | |||||
1. | Construction of flood protection wall for the protection of land of Washil Shah, Habib Shaha Bismillah Jan, Ajab Shah Kach on R/L of Tangi Algad Majeed Kach on Saraghazai Khuwara in Sherani Area F.R. D.I.Khan | 21.535
7/03/2018 |
Work reportedly in progress | Not yet conducted | 2nd / 3rd Week of March 2019 |
2. | Construction of flood protection bund for the protection of land of Tairza Khullah algad, Tehsil Wana, South Waziristan Agency | 3.90
7/03/2018 |
Nil | – | 2nd / 3rd Week of March 2019 |
3. | Construction of flood protection bund for protection of land of Gahazai Payaza, Tehsil Wana
South Waziristan Agency |
4.092
7/03/2018 |
Nil | – | 2nd / 3rd Week of March 2019 |
4. | Flood protection scheme at Ashraf Khel, Wana,
South Waziristan Agency |
4.841
7/03/2018 |
Nil | – | 2nd / 3rd Week of March 2019 |
VII | AZAD JAMMU & KASHMIR | ||||
2016-17 | |||||
1. | Construction of guide wall for protection of Khandaq right to Munawar forward situated along right bank of river Munawar Tawi, District Bhimber | 108.622
03/05/2017 |
– | 4th Week of April 2019 | |
2017-18 & 2018-19 | |||||
2. | Extension of existing flood protection structures at Bararkot left bank of River Kunhar,
District Muzaffarbad |
15.761 |
PC-I under process for approval
(Site visit in 4th Week of April 2019) |
||
Chief Engineering Adviser/Chairman Federal Flood Commission, Building No. 6, Ataturk Avenue, Sector G-5/1, Islamabad.
Tel : (+92) 51 9244616
Fax : (+92) 51 9244621
Email: info@ffc.gov.pk